Stadtwerke Augsburg (swa) has taken another step towards commissioning the underground tram link at Augsburg Hauptbahnhof (Main Railway Station). On 28 October 2026, a tram completed the first test run through the newly constructed turning loop in the station tunnel. The main focus was on testing the train protection system, which is intended to ensure safe tram operations in the tunnel and station areas in the future.

Train Protection System Tested Under Real Operating Conditions

During the first test run, swa tested how key technical systems interact under real operating conditions. The train protection system monitors, among other things, vehicle positions and the authorisation of routes. It ensures that trams only enter authorised sections of track and helps maintain compliance with permitted speed limits.

The test run took place behind closed doors, with no public access. Beforehand, the rails in the tunnel and station area were cleaned using a rail-grinding vehicle. According to swa, the first run was successful and confirmed that the installed systems were functioning correctly. Further test runs are scheduled to begin in mid-November 2026.

© swa / Thomas Hosemann

Construction work progressing

Alongside the technical tests, fitting-out work at the underground tram stop is continuing. Ceiling elements are currently being installed in the stairwells. Work on the wall panelling and floor coverings in the future station area has already been completed.

Before the planned opening in summer 2027, further construction work must be completed, alongside extensive technical testing and approval procedures. These include testing the smoke extraction system for use in the event of a fire, ensuring that the overhead line equipment meets the required standards, and checking the operation of safety-critical systems.

The operational requirements for running trams through the tunnel must also be put in place. From early 2027, swa plans to train around 340 tram drivers and a further 30 traffic supervisors to meet the specific requirements of underground operations.

Important milestone for Augsburg’s Integrated Mobility Hub

The underground tram stop is a key component of Augsburg’s integrated mobility hub. It is intended to make transfers between the railway network and the city’s tram system easier and fully accessible within the main station.

Under current plans, tram routes 3 and 4 will initially serve the underground stop and turn around using the turning loop. Full commissioning remains dependent on the completion of construction work and the successful completion of all tests and approval procedures.

(Info: swa)

© swa / Thomas Hosemann